Tuesday, June 7, 2011

Things are moving along..

Things seem to be moving along quiet well. Bricks are around 80% complete, Boris was down there over the weekend putting in a few extra studs on some load bearing walls for piece of mind and creating a niche in the hallway for Mel 

I was putting in extra noggins for mounting speakers in theatre room and TV's on other internal walls. 

Electricians had been out yesterday and roughed in all there wiring. Plumbers have been in today running more pipe work for toilets, showers, sinks etc.

All network,TV,Foxtel.HDMI and speaker cables to be ran Saturday by my cable guy, Laz, Drew and myself. There are a fair few to be ran.

Roof tiles 99% complete. 3 Tiles we have found have cracks that will be replaced.














Please enjoy the pics.

Steve and Mel