Friday, June 24, 2011

Cables are now installed

Sorry its been a little while. I have been busy installing cables and getting everything right prior to plaster install. Plaster actually went in today, I'll post those pictures shortly.












Tuesday, June 7, 2011

Things are moving along..

Things seem to be moving along quiet well. Bricks are around 80% complete, Boris was down there over the weekend putting in a few extra studs on some load bearing walls for piece of mind and creating a niche in the hallway for Mel 

I was putting in extra noggins for mounting speakers in theatre room and TV's on other internal walls. 

Electricians had been out yesterday and roughed in all there wiring. Plumbers have been in today running more pipe work for toilets, showers, sinks etc.

All network,TV,Foxtel.HDMI and speaker cables to be ran Saturday by my cable guy, Laz, Drew and myself. There are a fair few to be ran.

Roof tiles 99% complete. 3 Tiles we have found have cracks that will be replaced.














Please enjoy the pics.

Steve and Mel

Wednesday, May 25, 2011

Monday, May 16, 2011

Garage Roof trusses installed and external doors fitted.

Hi, I Just drove past the block before before and the builders had just left. All external doors are now fitted and garage roof trusses and lintels are now installed. The front door isnt the one we are getting its obviously a temp door due to doors probably being knocked off. Here are the pics.








Wednesday, May 11, 2011

Garage Wall/Part retaining wall Installed

Hi,
Garage wall has now been installed and as you can see there is double brick up to the neighbours soil height this is also a retaining wall.

Hopefully the builders come back tomorrow to finish of framing the garage and roof trusses for the garage.










Wednesday, May 4, 2011

Windows in and external doors and bricks delivered.

Hi,
Everything appears to be moving a long at a steady pace. Windows have been installed and all bricks delivered. Our guess is that they are going to brick the garage first so that the garage roof trusses can be joined to the rest of the house frame.They will then probably get the roof tiles up and finish bricking the rest of the house. Framing completion should be finished by next week i would think if they can get the brick layers in to do the garage.

Anyway here are some pictures